Banding Replacement

Image of concrete banding to a school building

The concrete banding at West Running Brook requires replacement due to cracking, delamination, spalling, displacement, bowing, and failed mortar joints. Budgeted amount: $2,589,616

Banding Replacement Timeline

 

March 2025-Bid Packets sent to 5 prospective qualified bidders.

 

 

April 8, 2025-Bid Awarded to Contracting Specialists Inc.

 

 

May 2025-Construction Begins

  • Brick and mortar selection completed
  • Scaffolding started May 11th and will continue through June
 

June 16, 2025-Contractor materials will be onsite

 

 

June 17, 2025-Demolition begins